EV Charging Infrastructure · Applied exercise

Frame a 10-unit, 60 kW charging project

A client asks for ten 60 kW chargers without vehicle schedules or confirmed electrical capacity.

EXPECTED DELIVERABLEA feasibility brief covering mobility demand, connected and managed load, upstream infrastructure, whole-site CAPEX, phasing and acceptance.
  1. 01Record the evidence
  2. 02Name assumptions and risks
  3. 03Choose the decision gate
Your draft stays on this device unless you download it or choose to request review.
Integrated DC fast charger with a pedestal unit, manufacturer render
Manufacturer renderEquipment in this course · DC fast charger

WorkbookEducational exercise

Record the evidence, then score it.

Four required inputs, three short syntheses and a four-part self-review. Save or download at any point; the review request opens when every item is complete.

PART 1 · EVIDENCE AND ANALYSIS

Build the decision from the required inputs.

State what is known, what remains assumed and what evidence would change the decision.

PART 2 · PROFESSIONAL SELF-REVIEW

Score the evidence, not the effort.

Use 0 when evidence is absent, 1 when it is only named, 2 when it is explained with a source or method, and 3 when it is strong enough to support the next decision.

Mobility basis

Calculates energy by departure rather than selecting chargers first.

Score Mobility basis
Demand control

Separates 600 kW connected load from an enforced managed limit.

Score Demand control
Whole-site scope

Includes transformer, protection, cabling, civil, software and support.

Score Whole-site scope
Phasing

Defines evidence-based expansion triggers.

Score Phasing
Score all criteria

Choose one evidence status for every criterion. A result appears only after all criteria are scored.

MODEL-ANSWER GUIDANCECompare your structure after completing the exercise.+
01

Build the charger mix from vehicle energy deadlines and acceptance curves.

02

Treat 600 kW as connected load; set a managed cap only after site capacity is verified.

03

Include upstream electrical, civil, connectivity, backend, permits, commissioning and lifecycle support.

04

Phase expansion using utilization, departure compliance and measured capacity headroom.

WORKBOOK COMPLETION1 of 14 requirements complete

Finish 13 requirements before requesting review.

You can save or download an incomplete draft at any time. The review request becomes available only when every required response and self-review score is complete.

Show the remaining requirements 13
  • Prepared by
  • Organization
  • Evidence response 1
  • Evidence response 2
  • Evidence response 3
  • Evidence response 4
  • Stated assumptions
  • Risks and missing evidence
  • Recommended decision and gate
  • Mobility basis self-review score
  • Demand control self-review score
  • Whole-site scope self-review score
  • Phasing self-review score
INCOMPLETE EDUCATIONAL DRAFT
Complete all listed items to request Metro Power review.