Calculates energy by departure rather than selecting chargers first.
EV Charging Infrastructure · Applied exercise
Frame a 10-unit, 60 kW charging project
A client asks for ten 60 kW chargers without vehicle schedules or confirmed electrical capacity.
Build the decision from the required inputs.
State what is known, what remains assumed and what evidence would change the decision.
Score the evidence, not the effort.
Separates 600 kW connected load from an enforced managed limit.
Includes transformer, protection, cabling, civil, software and support.
Defines evidence-based expansion triggers.
MODEL-ANSWER GUIDANCECompare your structure after completing the exercise.+
Build the charger mix from vehicle energy deadlines and acceptance curves.
Treat 600 kW as connected load; set a managed cap only after site capacity is verified.
Include upstream electrical, civil, connectivity, backend, permits, commissioning and lifecycle support.
Phase expansion using utilization, departure compliance and measured capacity headroom.