EV Charging Infrastructure · Applied exercise

Frame a 10-unit, 60 kW charging project

A client asks for ten 60 kW chargers without vehicle schedules or confirmed electrical capacity.

PART 1 · EVIDENCE AND ANALYSIS

Build the decision from the required inputs.

State what is known, what remains assumed and what evidence would change the decision.

PART 2 · PROFESSIONAL SELF-REVIEW

Score the evidence, not the effort.

Mobility basis

Calculates energy by departure rather than selecting chargers first.

Score Mobility basis
Demand control

Separates 600 kW connected load from an enforced managed limit.

Score Demand control
Whole-site scope

Includes transformer, protection, cabling, civil, software and support.

Score Whole-site scope
Phasing

Defines evidence-based expansion triggers.

Score Phasing
Score all criteria

Foundation draft. Revisit the lessons and evidence requirements.

MODEL-ANSWER GUIDANCECompare your structure after completing the exercise.+
01

Build the charger mix from vehicle energy deadlines and acceptance curves.

02

Treat 600 kW as connected load; set a managed cap only after site capacity is verified.

03

Include upstream electrical, civil, connectivity, backend, permits, commissioning and lifecycle support.

04

Phase expansion using utilization, departure compliance and measured capacity headroom.

COMPLETE ALL ANALYSIS SECTIONS